• Placed 72’ of 12” Ductile pipe ending the week at Station 114+88
• Ledge continues to be encountered with average of 1-3 feet removed to maintain 6’ of cover
• Temporary water lines have been chlorinated and will be tested beginning Monday the 18th
• Expectations are that once temporary water is on line the contractor will be placing a second crew on the project, a guess is within 2 weeks
• Current trench excavation will be completed up to 114+88 which is across from 42 Main Street
• Contractor will begin excavation crossing Main Street to come within 5-7 feet for the Silver Street connection without connecting to the existing butterfly valve
• Once that is complete excavation should resume on the 12” main working towards Common Street